Floating Structures at Collyer Quay (Extension of works)

Date of Notice : 13 Feb 2012
Period of Works : Extended till 31 Oct 2012
Location : Marina Bay (off One Fullerton)
Contractor : Marina Technology and Construction Pte Ltd
Crafts : SZ 15527C
Contact : Mouille Vincent @ 96625269 and Asher Lum @ 9009 7507

1.  This notice supersedes the notice dated  06  Jul 2011.

http://www.pub.gov.sg/marina/AllAnnouncements/Pages/FloatingStructuresatCollyerQuay(Extensionofworks).aspx 

The installation and erection works has been extended till 15 Oct 2012. The demobilisation works shall be up to 31 Oct 2012. Table 1 shows the revised Construction Project Schedule. Table 2 shows the coordinates of the construction work boundaries and various characteristics of marker buoys. Figure 1 shows the limits of the construction boundaries.

2. The limits of the work area remain unchanged. All vessels are to keep clear of the construction boundaries during the project duration.   

                                     Table 1- Construction Project Schedule

 
 

Duration

Work Time

15 Feb  to 15 Oct 2012

Installation & Erection of SPA/Conference Pods

0000hrs to 2400hrs

9 Feb to 15 Feb 2012

Demobilisation and Removal of marker buoys

 0000hrs to 2400hrs

 

 

Figure 1 - Construction boundary from 15 Feb 2012 to 31 Oct 2012