Floating Structures at Collyer Quay
| Date of Notice |
: 15 Nov 2010 |
| Period of Works |
: 19 Nov 2010 to 14 Jul 2011 |
| Location |
: Marina Bay (off One Fullerton) |
| Contractor |
: Marina Technology and Construction Pte Ltd |
| Crafts |
: SZ 15527C, ST 0455J and RC 955 (barge) |
| Contact |
: Mouille Vincent @ 96625269 and Asher Lum @ 9009 7507 |
1. This project is associated with the development of the Floating Structures at Collyer Quay. The Works will include fabrication & installation of floating structures, a pivot bridge, reinforced concrete works, utilizing floating crane barges, and associated support marine equipment. Table 1 shows the Construction Project Schedule.
2. The limits of the construction boundaries , are marked by points A, B, C, D, E, F, G, H & I. Orange Marker Buoys with yellow lights will be located at points B & C as shown on the location plan.
3. Table 2 shows the coordinates of the construction work boundaries and various characteristics of marker buoys. Figure 1 shows the limits of the construction boundaries that are marked by points A, B’, C’, D, E, F, G, H & I from 19 Nov to 07 Jan 2011 due to the preparation and conduct of Singapore Countdown 2010/2011. Figure 2 shows the actual Working Zone from 08 Jan 2011 onwards.
4. All vessels are to keep clear of the construction boundaries during the project duration.
Table 1- Construction Project Schedule
|
Start date |
Work |
Time |
|
19 Nov 2010 |
Mobilisation including installation of marker buoys |
0000hrs to 2400hrs |
|
21 Nov 2010 to 30 Jun 2011 |
Installation Works |
0000hrs to 2400hrs |
|
1 Jul 2011 to 14 Jul 2011 |
Demobilisation of barges etc. |
0000hrs to 2400hrs |

Figure 1 - Construction boundary from 19 Nov 2010 to 07 Jan 2011
2
Figure 2 - Construction boundary from 08 Jan 2011 onwards

|
|