Floating Structures at Collyer Quay

Date of Notice : 15 Nov 2010
Period of Works : 19 Nov 2010 to 14 Jul 2011
Location : Marina Bay (off One Fullerton)
Contractor : Marina Technology and Construction Pte Ltd
Crafts : SZ 15527C, ST 0455J and RC 955 (barge)
Contact : Mouille Vincent @ 96625269 and Asher Lum @ 9009 7507

1. This project is associated with the development of the Floating Structures at Collyer Quay. The Works will include fabrication & installation of floating structures, a pivot bridge, reinforced concrete works, utilizing floating crane barges, and associated support marine equipment. Table 1 shows the Construction Project Schedule.

2. The limits of the construction boundaries , are marked by points A, B, C, D, E, F, G, H & I. Orange Marker Buoys with yellow lights will be located at points B & C as shown on the location plan.

3. Table 2 shows the coordinates of the construction work boundaries and various characteristics of marker buoys. Figure 1 shows the limits of the construction boundaries that are marked by points A, B’, C’, D, E, F, G, H & I from 19 Nov to 07 Jan 2011 due to the preparation and conduct of Singapore Countdown 2010/2011. Figure 2 shows the actual Working Zone from 08 Jan 2011 onwards.

4. All vessels are to keep clear of the construction boundaries during the project duration.   

                                     Table 1- Construction Project Schedule

 

Start date

Work Time

19 Nov 2010

Mobilisation including installation of marker buoys

0000hrs to 2400hrs

21 Nov 2010 to 30 Jun 2011

Installation Works

0000hrs to 2400hrs

1 Jul 2011 to 14 Jul 2011

Demobilisation of barges etc.

 0000hrs to 2400hrs

 

Figure 1 - Construction boundary from 19 Nov 2010 to 07 Jan 2011

2

Figure 2 - Construction boundary from 08 Jan 2011 onwards