RECENT FLASH FLOODS

20 Mar 2014

Due to the heavy rain this afternoon, flash flood occurred at the following location.

Region Location Extent Findings & Follow-ups
Eastern Yishun Ave 2 / Yishun Ave 5 (slip road)

Depth: 150mm
Width: 1 lane
Length: 30m

Passable to traffic

Intense rain caused flooding at this location.

PUB has plans to improve the drainage at this area. Work is expected to commence 2Q 2014.

18 Dec 2013

Due to the heavy rain this afternoon, flash floods occurred at the following locations.

Region Location Extent Findings & Follow-ups
Central Jalan Seaview

Depth: 150mm
Width: 2 lanes
Length: 30m

Passable to traffic

Intense rain caused flooding at this low-lying area.

Drainage improvement works are in progress and are expected to complete in 3Q 2014.

Eastern Yishun Ave 2 / Yishun Ave 5 (slip road)

Depth: 150mm
Width: 1 lane
Length: 30m

Passable to traffic

Intense rain caused flooding at this location.

PUB has plans to improve the drainage at this area. Work is expected to commence 2Q 2014.

Central

Road shoulder near centre median of PIE towards Changi (near Woodsville Flyover)

Depth: <50mm
Width: shoulder lane
Length: 10m

Passable to traffic

Intense rain caused flooding at this location.

PUB has plans to improve the drainage at this area.

 

 

15 Dec 2013

Due to the heavy rain this afternoon, flash flood occurred at the following location.

Region Location Extent Findings & Follow-ups
Eastern Chai Chee Road near junction of New Upper Changi Road

Depth: 150mm
Width: 2 lanes
Length: 30m

Passable to traffic

Heavy rain caused flooding at this known hotspot.

PUB has plans to improve the drainage at this area. Work is expected to commence mid 2014.

 

 

3 Dec 2013

Due to the heavy rain this afternoon, flash floods occurred at the following locations.

Region Location Extent Findings & Follow-ups
Western Hillview Avenue / Jalan Remaja junction

Depth: 200mm
Width: 2 lanes
Length: 50m

Passable to traffic

Intense rain caused flooding at this location.

PUB has plans to improve the drainage at this area. Work is expected to commence 1Q 2014.

Central Ang Mo Kio Ave 5 / Ang Mo Kio Industrial Park 2 junction

Depth: <50mm
Width: 1/2 lane
Length: 10m

Passable to traffic

Heavy rain caused flooding at this location.

There is on going works to improve the drainage system at Ang Mo Kio Ave 5.

 

 

30 Nov 2013

Due to the heavy rain this afternoon, flash floods occurred at the following locations.

Region Location Extent Findings & Follow-ups
Western Jalan Boon Lay (near International Road)

Depth: 300mm
Width: 2 lanes
Length: 100m

2 lanes impassable to traffic for 15mins.

Intense rain caused flooding at this location.

Western Enterprise Road

Depth: 300mm
Width: 2 lanes
Length: 100m

Passable to traffic

Intense rain caused flooding at this location.

Ongoing drainage improvement project is expected to complete by 1Q 2014

 

 

24 Nov 2013

Due to the heavy rain this afternoon, flash floods occurred at the following location.

Region Location Extent Findings & Follow-ups
Eastern Chai Chee Rd / New Upper Changi Rd junction

Depth: 150mm
Width: 2 lanes
Length: 30m

2 lanes impassable to traffic for 10mins.

Heavy rain caused flooding at this known hotspot.

PUB has plans to improve the drainage at this area. Work is expected to commence mid 2014.

 

 

23 Nov 2013

Due to the heavy rain this morning, flash floods occurred at the following location.

Region Location Extent Findings & Follow-ups
Eastern Sembawang Rd (in front of Sembawang Shopping Centre

Depth: 175mm
Width: 2 lanes
Length: 30m

Passable to traffic

Intense rain caused flooding at this location.

Ongoing drainage improvement project is expected to complete by 4Q 2013

 

13 Nov 2013

Due to the heavy rain this afternoon, flash floods occurred at the following locations.

Region Location Extent Findings & Follow-ups
Eastern Tampines Road (near Jalan Teliti)

Depth: 100mm
Width: 1 lane
Length: 30m

Passable to traffic

Intense rain caused flooding at this location.

There is on going works to improve the drainage system.

Western Slip road of PIE to AYE (towards city)

Depth: 200mm
Width: 2 lanes
Length: 100m

Passable to traffic

Intense rain caused flooding at this location.

 

5 Nov 2013

Due to the heavy rain this afternoon, flash floods occurred at the following locations.

Region Location Extent Findings & Follow-ups
Eastern Sembawang Rd (in front of Sembawang Shopping Centre

Depth: 175mm
Width:  3 lanes
Length: 100m

Passable to traffic

Intense rain caused flooding at this location.

Ongoing drainage improvement project is expected to complete by 4Q 2013

Eastern Chai Chee Rd / New Upper Changi Rd junction

Depth: 150mm
Width: 2 lanes
Length: 30m

Passable to traffic

Intense rain caused flooding at this known hotspot.

PUB has plans to improve the drainage at this area. Road raising works has commenced.

  

 

 
 
Last updated on 20 Mar 2014