| Date and Time | Location | Craft | Contact |
|---|---|---|---|
| Refer to schedule below | Kallang Basin, Marina Channel, and Marina Bay | RZ73, SR 3639J, SR 3876H, PCG boats, SAF General Support Boats, M3G Vessels |
Charlie Chua, NDP 2023 FW Committee Adam Tan (Glorious Singapore Pte Ltd) Kwek Teck Kee (Glorious Singapore Pte Ltd) |
1.Marina Bay will be closed to all water traffic for the National Day Parade (NDP) 2023 shows and fireworks displays on NDP rehearsals, previews and actual day.
2.Marina Bay will be closed between the Jubilee Bridge and Helix Bridge during the dates and times specified in Table 2. Two safety boats will be present at each closing limit to enact these closures. All vessels are not to cross the safety boats limit and follow the instructions and directions given by the safety boats’ crew. Please refer to the location maps here.
Table 2: Closure of Marina Bay to all Water Traffic
| Date | Event | Closure time | |
|---|---|---|---|
| 10-Jun | CR1 | 1730 hrs to 2100 hrs | |
| 17-Jun | CR2 | ||
| 24-Jun | CR3 | ||
| 2-Jul | NE1 | ||
| 8-Jul | NE2 | ||
| 15-Jul | NE3 |
||
| 22-Jul | P1 |
1730 hrs to 2200 hrs | |
| 29-Jul | P2 |
||
| 9-Aug | Actual | ||
3.There will be installation and removal works at the Kallang Basin (Republic Ave) and Marina Bay from 22 May to 22 Aug 2023. Please refer Table 3 below for the schedule of works and attached location maps.
Table 3: Details of Works at Kallang Basin and Marina Bay
| Date | Time | Activities | Safety Remarks | |
|---|---|---|---|---|
| 22 – 24 May | 1000 – 1800hrs | Towing pontoons/ Cubi system from WWS to Kallang Basin (Republic Ave) and set up works. | All vessels are to keep a wide berth to the towing operations and keep clear of set up areas. (Refer to Map 1) | |
| 22 – 26 May (*Reserve date 30 May) |
1000 – 1600hrs | Craning ops at Kallang Basin (Republic Ave) Configuration of cubi and pontoons at Kallang Basin (Republic Ave) *Reserve date for craning ops |
All vessels are to keep clear of setup areas. (Refer to Map 1). |
|
| 31 May – 3 Jun (*Reserve date 4 Jun) |
1000 – 1800hrs |
Towing of pontoons/ Cubi system from Kallang Basin (Republic Ave) to Marina Bay for positioning and anchoring. Safety lines using line of floats and red colour buoys with flashing lights and no-entry signs will be installed. *Reserve date for towing ops |
All vessels are to keep a wide berth to the towing operations and keep clear of set up areas. (Refer to Map 1, 2) |
|
| 7 Jun, 14 Jun, 21 Jun, 29 Jun, 05 Jul, 12 Jul, 18 Jul, 25 Jul, 5 Aug (*Reserve date 8, 15, 22, 30 Jun; 6, 13, 19, 26 Jul & 6 Aug) |
1000 – 1800hrs |
Transferring / towing of Mid cum high level fireworks from Republic Ave to Marina Bay for installation process. *Reserve date for transferring/ towing ops |
All vessels are to keep a wide berth to the towing operations and keep clear of set-up areas. (Refer to Map 1) |
|
|
7- 10 Jun, 14 -17 Jun, 21- 24 Jun, 29 Jun- 2 Jul, 5 – 8 Jul, 12 -15 Jul, 18- 22 Jul, 25- 29 Jul, 5 – 9 Aug |
1000 – 2000hrs |
Mid cum high level fireworks installation work in progress at Marina Bay site. Fireworks on site. |
All vessels are to keep a wide berth to the towing operations and keep clear of setup areas. All vessels are to follow the navigational route in Map 2 |
|
| 10 – 12 Aug (*Reserve date 13 Aug) |
1000 – 1800hrs |
Removal of safety lines, red colour buoys and no-entry signs at Marina Bay. De-installation of pontoons. Towing of pontoons/ Cubi system from Marina Bay back to Kallang Basin (Republic Ave) for dismantling. *Reserve date for towing ops |
All vessels are to keep a wide berth to the towing operations and keep clear of tear-down areas. (Refer to Map 1, 2) |
|
|
14 – 18 Aug (*Reserve date 21 Aug) |
1000 – 1600hrs |
Dismantling works at Republic Ave. Recovery craning ops at Kallang Basin (Republic Ave). *Reserve date for craning ops |
All vessels are to keep clear of the tear-down areas. (Refer to Map 1) |
|
| 21 Aug (*Reserve date 22 Aug) |
1000 – 1800hrs |
Towing pontoons/ Cubi system back to WWS from Kallang Basin (Republic Ave). Works at Republic Ave. (NDP 2023 – Wooden pontoons) *Reserve date for towing ops |
All vessels are to keep a wide berth to the towing operations and keep clear of the tear-down areas. (Refer to Map 1) |
|
1.Marina Bay will be closed to all water traffic for the National Day Parade (NDP) 2023 shows and fireworks displays on NDP rehearsals, previews and actual day.
2.Marina Bay will be closed between the Jubilee Bridge and Helix Bridge during the dates and times specified in Table 2. Two safety boats will be present at each closing limit to enact these closures. All vessels are not to cross the safety boats limit and follow the instructions and directions given by the safety boats’ crew. Please refer to the location maps here.
Table 2: Closure of Marina Bay to all Water Traffic
| Date | Event | Closure time | |
|---|---|---|---|
| 10-Jun | CR1 | 1730 hrs to 2100 hrs | |
| 17-Jun | CR2 | ||
| 24-Jun | CR3 | ||
| 2-Jul | NE1 | ||
| 8-Jul | NE2 | ||
| 15-Jul | NE3 |
||
| 22-Jul | P1 |
1730 hrs to 2200 hrs | |
| 29-Jul | P2 |
||
| 9-Aug | Actual | ||
3.There will be installation and removal works at the Kallang Basin (Republic Ave) and Marina Bay from 22 May to 22 Aug 2023. Please refer Table 3 below for the schedule of works and attached location maps.
Table 3: Details of Works at Kallang Basin and Marina Bay
| Date | Time | Activities | Safety Remarks | |
|---|---|---|---|---|
| 22 – 24 May | 1000 – 1800hrs | Towing pontoons/ Cubi system from WWS to Kallang Basin (Republic Ave) and set up works. | All vessels are to keep a wide berth to the towing operations and keep clear of set up areas. (Refer to Map 1) | |
| 22 – 26 May (*Reserve date 30 May) |
1000 – 1600hrs | Craning ops at Kallang Basin (Republic Ave) Configuration of cubi and pontoons at Kallang Basin (Republic Ave) *Reserve date for craning ops |
All vessels are to keep clear of setup areas. (Refer to Map 1). |
|
| 31 May – 3 Jun (*Reserve date 4 Jun) |
1000 – 1800hrs |
Towing of pontoons/ Cubi system from Kallang Basin (Republic Ave) to Marina Bay for positioning and anchoring. Safety lines using line of floats and red colour buoys with flashing lights and no-entry signs will be installed. *Reserve date for towing ops |
All vessels are to keep a wide berth to the towing operations and keep clear of set up areas. (Refer to Map 1, 2) |
|
| 7 Jun, 14 Jun, 21 Jun, 29 Jun, 05 Jul, 12 Jul, 18 Jul, 25 Jul, 5 Aug (*Reserve date 8, 15, 22, 30 Jun; 6, 13, 19, 26 Jul & 6 Aug) |
1000 – 1800hrs |
Transferring / towing of Mid cum high level fireworks from Republic Ave to Marina Bay for installation process. *Reserve date for transferring/ towing ops |
All vessels are to keep a wide berth to the towing operations and keep clear of set-up areas. (Refer to Map 1) |
|
|
7- 10 Jun, 14 -17 Jun, 21- 24 Jun, 29 Jun- 2 Jul, 5 – 8 Jul, 12 -15 Jul, 18- 22 Jul, 25- 29 Jul, 5 – 9 Aug |
1000 – 2000hrs |
Mid cum high level fireworks installation work in progress at Marina Bay site. Fireworks on site. |
All vessels are to keep a wide berth to the towing operations and keep clear of setup areas. All vessels are to follow the navigational route in Map 2 |
|
| 10 – 12 Aug (*Reserve date 13 Aug) |
1000 – 1800hrs |
Removal of safety lines, red colour buoys and no-entry signs at Marina Bay. De-installation of pontoons. Towing of pontoons/ Cubi system from Marina Bay back to Kallang Basin (Republic Ave) for dismantling. *Reserve date for towing ops |
All vessels are to keep a wide berth to the towing operations and keep clear of tear-down areas. (Refer to Map 1, 2) |
|
|
14 – 18 Aug (*Reserve date 21 Aug) |
1000 – 1600hrs |
Dismantling works at Republic Ave. Recovery craning ops at Kallang Basin (Republic Ave). *Reserve date for craning ops |
All vessels are to keep clear of the tear-down areas. (Refer to Map 1) |
|
| 21 Aug (*Reserve date 22 Aug) |
1000 – 1800hrs |
Towing pontoons/ Cubi system back to WWS from Kallang Basin (Republic Ave). Works at Republic Ave. (NDP 2023 – Wooden pontoons) *Reserve date for towing ops |
All vessels are to keep a wide berth to the towing operations and keep clear of the tear-down areas. (Refer to Map 1) |
|