| Date of Notice | 14 Dec 2023 |
|---|---|
| Date and Time | Refer to schedule below |
| Location | Kallang Basin, Marina Channel and Marina Bay |
| Craft |
SZ16948G, RZ57, Kairos boats (SZH1790C, SZ21711E, SZH1854C, SZH1749F, SZ21474D, SZH1690G, SZ20702J) |
| Contact |
Teng Mun Kit (Avex Asia Com Post) [email protected] Samson Phua (Intermay Consultech Pte Ltd) [email protected] Roy (Kairos Strategic Pte Ltd) [email protected] |
1. There will be installation and removal works in Kallang Basin and Marina Bay from 18th Dec 2023 to 5th Jan 2024. Please refer to the table below for the schedule of works, water closure and the location maps here.
2. Safety lines using line of floats, red colour buoys and no-entry signs with flashing lights will be installed from 23rd Dec 2023. These will mark the borders indicating the NO-ENTRY ZONES. All vessels are advised not to trespass into the NO-ENTRY ZONES and to ply strictly within the navigational route as set out in Map 2.
3. Marina Bay will be closed for water traffic between Jubilee Bridge and Helix Bridge from 31st Dec 2023, 2000hrs to 1st Jan 2024, 0200hrs. Safety boats will be present at each closure limit. All vessels are not to enter Marina Bay and stay behind the water barricades. All vessels are to comply with the instructions/ directions given by the safety/security boats’ crew and Police Coast Guard deployed.
| Date | Time | Works | Safety Remarks |
|---|---|---|---|
| 18th to 22nd December 2023 | 09:00hrs to 18:00hrs | Craning Operations (Unloading of pontoons/cubis system from lorry crane to Kallang Basin near Ducktours splash point) Configuration of pontoons/cubis and @ Kallang Basin near Ducktours splash point. |
All vessels are to keep a wide berth to the towing operations and keep clear of setup areas. (Refer to Map 1) |
| 23rd December 2023 (Reserve 24th December 2023) |
09:00hrs to 18:00hrs | Craning operations of general cargo container onto pontoons at Kallang Basin near Waterway Watch Society. Towing of pontoons/cubis system from Kallang Basin to firing site at Marina Bay for positioning / anchoring and installation of safety cordon. |
All vessels are to keep a wide berth to the towing operations and keep clear of setup areas. (Refer to Map 1) |
| 24th & 25th December 2023 | 09:00hrs to 18:00hrs |
Setup Works at Marina Bay. |
All vessels are to keep a wide berth to the towing operations and keep clear of setup areas. (Refer to Map 1) |
| 26th December 2023 (Reserve 27th December 2023) |
09:00hrs to 18:00hrs |
Craning operations of fireworks container onto pontoons at Kallang Basin near Waterway Watch Society. Towing of fireworks container from Kallang Basin to Marina Bay for installation process. |
All vessels are to keep a wide berth to the towing operations and keep clear of setup areas. (Refer to Map 1) |
| 30th December 2023 to 31st December 2023 |
10:00hrs to 20:00hrs |
Installation of water barricades at the two closure limits using Kairos boats (Jubilee and Helix bridge). |
All vessels are to keep clear of setup areas. |
| 31st December 2023 to 1st January 2024 |
31st December 2023, 2000hrs to 1st January 2024, 0200hrs |
D Day – Full closure at Marina Bay (water barricades at the two closure limits effective) |
All vessels are not to enter Marina Bay and stay behind the water barricades. All vessels are to comply with the instructions/ directions given by the safety/security boats’ crew and Police Coast Guard deployed. (Refer to Map 3) |
| 31st December 2023 to 1st January 2024 |
31st December 2023, 2230hrs to 1st January 2024, 0030hrs |
Show time with fireworks displays |
All vessels are not to enter Marina Bay and stay behind the water barricades. All vessels are to comply with the instructions/ directions given by the safety/security boats’ crew and Police Coast Guard deployed. (Refer to Map 3) |
| 1st January 2024 |
02:00hrs to 04:00hrs |
Removal of water barricades at Marina Bay at the two closure limits using Kairos boats (Jubilee and Helix bridge). |
All vessels are to keep clear of tear-down areas. |
| 1st January 2024 to 2nd January 2024 (Reserve 3rd January 2024) |
09:00hrs to 18:00 hrs |
De-Installation of pontoons. Towing of pontoons/cubis system from Marina Bay back to Kallang Basin near Ducktours splash point for dismantling. |
All vessels are to keep a wide berth to the towing operations and keep clear of tear-down areas. (Refer to Map 1) |
| 2nd January 2024 to 5th January 2024 |
09:00hrs to 18:00 hrs |
De-Installation of pontoons. Craning operation to remove pontoons/cubis system back to storage. |
All vessels are to keep a wide berth to the towing operations and keep clear of tear-down areas. (Refer to Map 1) |