Inspection of Floating Structures at Collyer Quay
|
Date of Notice |
20 May 2024 |
|
Period of Work |
21 to 24 May 2024 |
|
Time |
0900hrs to 1900hrs |
|
Location |
Marina Reservoir, Fullerton Bay Hotel at Collyer Quay |
|
Craft |
Nil |
|
Contact Person |
Delta Marine Consultants Singapore
Raymond Ling - 81338388
William Ong - 81290271 |
1. Delta Marine Consultants Singapore Pte Ltd is the appointed consultant by Fullerton Bay Hotel Singapore. Aedge Technologies Pte Ltd is the appointed diver team.
2. This notice is to inform on the inspection (above water and underwater) of the floating structures of entertainment pod, conference pod and SPA pods at Collyer Quay, Singapore.
3. The location of the above structures is shown below.
4. The work involves accessing the underside of floating structures by divers to check the structures conditions and record photographs.
5. All vessels are advised to keep clear of the inspection work areas and slow down when in the vicinity.
6. The schedule of works is shown below.
|
Date |
Inspection Location |
Working Hours |
|
21 to 24 May 2024 |
Floating Structures at Collyer Quay (Entertainment Pod, Conference Pod & SPA Pods) |
0900hrs to 1900hrs |