LTA Contract TR370 - Painting of Bridge Elements Along Singapore River
|
Date of Notice |
3 June 2024 |
|
Period of Work |
3 June 2024 to 31 March 2025 (Refer to schedule below) |
|
Time |
0800hrs to 1900hrs |
|
Location |
Marina Reservoir (Anderson Bridge, Cavanagh Bridge, Elgin Bridge, Coleman Bridge, Read Bridge, Ord Bridge, Clemenceau Bridge, Robertson Bridge and Jiak Kim Bridge) |
|
Craft |
RC 215 RC 486 RC 481
|
|
Contact Person |
CHC Construction Pte. Ltd.
|
1. The following painting of bridge elements across the 9 bridges along Singapore River will be carried out by LTA appointed maintenance contractor, CHC Construction Pte. Ltd. from 3 June 2024 to 31 March 2025 (0800hrs to 1900hrs).
2. The schedule of works
|
Item |
Description |
Date |
|
1 |
Painting of Anderson Bridge |
3 June to 3 July 2024 |
|
2 |
Painting of Cavanagh Bridge |
3 July to 3 August 2024 |
|
3 |
Painting of Elgin Bridge |
3 August to 3 September 2024 |
|
4 |
Painting of Coleman Bridge |
3 September to 3 October 2024 |
|
5 |
Painting of Read Bridge
|
3 October to 3 November 2024 |
|
6 |
Painting of Ord Bridge
|
3 November to 3 December 2024 |
|
7 |
Painting of Clemenceau Bridge
|
3 December 2024 to 3 January 2025 |
|
8 |
Painting of Robertson Bridge
|
3 January to 3 February 2025 |
|
9 |
Painting of Jiak Kim Bridge |
3 February to 3 March 2025 |
|
10 |
Inspection of work completion with authorities |
3 March to 31 March 2025 |