RESERVOIR NOTICE

 

Date of Notice

3 Dec 2024

Dateand Time

Refer to schedule below

Location

Kallang Basin, Marina Channel and Marina Bay

Craft

RZ92, RZ57, Kairos boats (SZ20390D, SZH1794F, SZH1692C, SZH1691E, SZH1690G, SZ21899E, SZH1790C)

Contact

Yoshimasa Hayashi (Avex Asia Com Post)

[email protected]

 

Samson Phua (Intermay Consultech Pte Ltd)

s[email protected]

 

Roy (Kairos Strategic Pte Ltd)

[email protected]

 

1.             There will be installation and removal works in Kallang Basin & Marina Bay from 4 Dec 2024 to 7 Jan 2025. Please refer to the table below for the schedule of works, water closure and the location maps here.


2.             Safety lines using line of floats, red colour buoys and no-entry signs with flashing lights will be installed from 11 Dec 2024. These will mark the borders indicating the NO-ENTRY ZONES. All vessels are advised not to trespass into the NO-ENTRY ZONES and to ply strictly within the navigational route as set out in Map 2.

 

3.             Marina Bay will be closed for water traffic between Jubilee Bridge and Helix Bridge from 31 Dec 2024, 2000hrs to 1 Jan 2025, 0200hrs. Safety boats will be present at each closure limit. All vessels are not to enter Marina Bay and stay behind the water barricades. All vessels are to comply with the instructions/ directions given by the safety/security boats’ crew and Police Coast Guard deployed.

 

Date

Time

Activities

Safety Remarks

4 to 11 December 2024

 

09:00hrs – 18:00hrs

 

Craning Operations (Unloading of pontoons/cubis system from lorry crane to Kallang Basin (Republic Ave)

 

Configuration of pontoons/cubis and at Kallang Basin (Republic Ave)

All vessels are to keep clear of setup areas. (Refer to Map 1)

11 to 20 December 2024

 

 

 

 

 

 

 

09:00hrs to 18:00hrs

 

 

 

 

 

 

Craning operations of general cargo container onto pontoons at Kallang Basin (Republic Ave)

 

Towing of pontoons/cubis system from Kallang Basin to firing site at Marina Bay for positioning / anchoring and installation of safety cordon.

All vessels are to keep a wide berth to the towing operations and keep clear of setup areas. (Refer to Map 1)

23 to 31 December 2024

09:00hrs to 18:00hrs

Craning operations of fireworks container onto pontoons at Kallang Basin (Republic Ave)

 

Towing of fireworks container from Kallang Basin to Marina Bay for installation process.

All vessels are to keep a wide berth to the towing operations and keep clear of setup areas. (Refer to Map 1)

11 to 29 December 2024

09:00hrs to 18:00hrs

Setup works at Marina Bay site

All vessels are to keep clear of setup areas. (Refer to Map 2)

30 December 2024 to 31 December 2024

10:00hrs to 20:00hrs

Installation of water barricades at the two closure limits using Kairos boats (Jubilee and Helix bridge)

All vessels are to keep clear of setup areas.

31 December 2024 to 1 January 2025

 

 

 

31 December 2024, 20:00 hrs to 1 January 2025, 02:00hrs

 

 

 

 

D Day – Full closure at Marina Bay (water barricades at the two closure limits effective)

 

 

 

All vessels are not to enter Marina Bay and stay behind the water barricades.

All vessels are to comply with the instructions/ directions given by the safety/security boats’ crew and Police Coast Guard deployed.

(Refer to Map 3)

31 December 2024 to 1 January 2025

 

31 December 2024, 23:00 hrs to 1 January 2025, 00:30hrs

Show time with fireworks displays

All vessels are not to enter Marina Bay and stay behind the water barricades. All vessels are to comply with the instructions/ directions given by the safety/security boats’ crew and Police Coast Guard deployed.

(Refer to Map 3)

1 January 2025

02:00hrs to 04:00hrs

Removal of water barricades at Marina Bay at the two closure limits by Kairos boats (Jubilee and Helix bridge).

All vessels are to keep a wide berth to the towing operations and keep clear of tear-down areas. (Refer to Map 1)

1 January 2025 to

3 January 2025

(Reserve date 4 Jan)

09:00hrs – 18:00 hrs

De-Installation of pontoons at Marina Bay.

 

Towing of pontoon/cubis system from Marina Bay back to Kallang Basin (Republic Ave) for dismantling.

All vessels are to keep a wide berth to the towing operations and keep clear of tear-down areas. (Refer to Map 1)

3 January 2025 to 7 January 2025

09:00hrs – 18:00 hrs

De-Installation of pontoons at Kallang Basin (Republic Ave).

 

Craning operation to remove pontoons/cubis system back to storage.

All vessels are to keep clear of tear-down areas. (Refer to Map 1)