Date of Notice |
1 April 2025 |
|
Period of Work |
1 to 6 April 2025 |
|
Time |
0830hrs to 2030hrs |
|
Location |
Marina Reservoir, Benjamin Sheares Bridge |
|
Craft |
RC467 Catamaran Flotsam Retriever and RC475 Work Boat (Back up) |
|
Contact Person |
Guthrie Engineering Pte Ltd Saravanan 84295502 |
1. Guthrie Engineering Pte Ltd has been engaged by LTA to carry out rectification of LED lightings at vehicular bridge at Benjamin Sheares Bridge from 1 April to 6 April 2025. Please refer to the table below for the schedule of works and activities.
2. The schedule of works
|
Activities |
Start date / Time |
End date / Time |
|
Mobilisation of work boat |
1 April 2025 / 0830hrs |
6 April 2025 / 2030hrs |
|
LED Lighting Rectification works |
1 April 2025 / 0830hrs |
6 April 2025 / 1630hrs |
|
De-mobilisation of work boat |
6 April 2025 / 2030hrs |
6 April 2025 / 2030hrs |
3. The location of works

4. Photos of Work Boats
Photo of RC 467 Catamaran Flotsam Retiever

Photo of RC 475 Workboat

- After completing the daily work, the work boat will be anchored at the bridge abutment wall.
- All vessels are advised to keep clear of the inspection work areas and slow down when in the vicinity.