Date and Time

Refer to schedule below

 

Location

Kallang Basin, Marina Channel, and Marina Bay

 

Craft

RZ100, RZ57, SZ 15477C

 

Contact

Samson Phua (Intermay Consultech Pte Ltd)

[email protected]

 

Roy Lim (Intermay Consultech Pte Ltd)

r[email protected]

 

 

 

1.              There will be installation and removal works at the Kallang Basin (Republic Ave) and Marina Bay from 1 September 2025 to 16 October 2025. Please refer Table 1 for the works schedule and map for details.

 

 

                           Table 1: Details of Works at Kallang Basin and Marina Bay

 

Date

Time

Activities

Safety Remarks

01/09/2025 to 17/09/2025

0700hrs to

1900hrs

Craning Ops at Kallang Basin (Republic Ave).

 

Configuration of cubis and pontoons at Kallang Basin (Republic Ave).

 

All vessels are to keep clear of setup areas.

(Refer to Map)

17/09/2025

 

(*Reserve date 18/09/2025)

0700hrs to 1900hrs

Towing of pontoons/ Cubi system from Kallang Basin (Republic Ave) to Marina Bay for positioning and anchoring.

 

Safety lines using lines of floats and buoys with flashing lights and no-entry signs will be installed. These will mark the borders indicating the NO-ENTRY ZONE.

 

*Reserve date for towing ops

 

All vessels are to keep a wide berth to the towing operations and keep clear of set up areas. (Refer to Map)

 

19/09/2025 to 05/10/2025

0700hrs to 2300hrs

 

Show preparation, rehearsal and show dates.

 

 

All vessels are to keep clear of No-entry zone.

(Refer to Map)

06/10/2025

 

(*Reserve date 07/10/2025)

0700 – 1900hrs

Removal of safety lines, buoys and no-entry signs at Marina Bay. De-installation of pontoons.

 

Towing of pontoons/ Cubi system from Marina Bay back to Kallang Basin (Republic Ave) for dismantling.

 

*Reserve date for towing ops

 

All vessels are to keep a wide berth to the towing operations and keep clear of tear-down areas. (Refer to Map)

06/10/2025 to 16/10/2025

0700 – 1900hrs

Dismantling works and recovery craning ops at Kallang Basin (Republic Ave).

 

All vessels are to keep clear of the tear-down areas. (Refer to Map)

 

 

Safety Measures

 

2.                From 18 September onwards, there will be anchoring and setting up of the barricaded area using lines of floats, buoys with flashing lights and no-entry signs in Marina Bay (off Esplanade Outdoor Theatre). These will mark the borders indicating the NO-ENTRY ZONE.

 

3.               All vessels are advised not to trespass into the NO-ENTRY ZONE and to ply outside the safety lines at all times.

 

 

Location map and works schedule