Date of Notice

3 September 2025

Period of Work

15 September 2025 to 30 November 2025

Time

08:30hrs to 18:30hrs

Location

Marina Reservoir (Opposite of Flower Dome)

Craft

RC467 Catamaran Flotsam Retriever and RC908 Work Boat (Back up)

Contact Person

Santarli Construction Pte Ltd (Main-Contractor)

Soe Hlaing Moe (9895 0419)

 

EE Fong Construction Pte Ltd (Sub-Contractor)

Zaw Win Thein (9899 5243)

 

 

  1. Santarli Construction Pte Ltd has been appointed as the builder for Development of Bay East Gardens by Ministry of National Development (MND) and Gardens by the Bay (GB). A 500mm diameter of intake pipe shall be installed from Marina Reservoir to Bay East Garden for irrigation purpose/system of gardens. Approximately 6m width of existing rock revetment at Marina Reservoir shall be removed in order to facilitate the pipe installation. Santarli Construction Pte Ltd has engaged the specialist sub-contractor, EE Fong Construction Pte Ltd to carry out the removal and reinstatement of rock revetment at Marina Reservoir.

     

  2. The schedule of works

    Activities

    Start date / Time

    End date / Time

    Mobilization of work boat

    15 Sep 2025

    25 Sep 2025

    Deployment an installation of Silt Barricade

    15 Sep 2025

    25 Sep 2025

    Deployment of Machineries to Promenade Road and Preparation Works

    27 Sep 2025

    5 Oct 2025

    Removal and reinstatement of revetment

    6 Oct 2025

    25 Nov 2025

    Demobilization of machineries, including dismantling of silt barricade.

    26 Nov 2025

    30 Nov 2025

  3. The location of works

     

  4. Photos of Work Boats

Photo of RC 467 Catamaran Flotsam Retiever

Photo of RC 908 Workboat

  • After the completion of daily work, the workboat will be anchored at the bridge abutment wall