Date of Works |
16 to 23 December 2025 |
|
Time |
0900hrs to 1700hrs |
|
Location |
Fullerton Bay Hotel at Collyer Quay, Singapore |
|
Craft |
- |
|
Contact Person |
Randy Lim @ 96866304 (Lerwick Corrosion Technologies Pte. Ltd)
Ryan Delaney Tan @ 90011619 (Straits Diving & Engineering Pte. Ltd) |
1. Lerwick Corrosion Technologies Pte. Ltd is the appointed contractor by Fullerton Bay Hotel Singapore. Straits Diving & Engineering Pte. Ltd is the appointed diver team.
2. This is to inform on the cathodic protection (CP) repair work of the floating structures of conference pod and SPA pods at Collyer Quay, Singapore
3. The location of the above structures is shown below.

4. The work involves accessing the underside of floating structures by divers to replace/install CP anodes and record photographs.
5. All vessels are advised to keep clear of the inspection work areas and slow down when in the vicinity.
6. The schedule of works is shown below.
|
Date |
Cathodic Protection Repair Work Location |
Working Hours |
|
16 – 23 Dec 2025 |
Floating Structures at Collyer Quay (Conference Pod & SPA Pods) |
0900hrs to 1900hrs |