Period of Work |
16 Dec 2025 to 26 Dec 2025 |
|
Time |
08:30hrs to 18:30hrs |
|
Location |
Marina Reservoir (Near Event Plaza, Under Benjamin Sheares Bridge) |
|
Craft |
RC467 Catamaran Flotsam Retriever, and RC908 and RC910 Work Boat (Back up) |
|
Contact Person |
Santarli Construction Pte Ltd (Main- Contractor)
Soe Hlaing Moe (9895 0419) Jahidul (8670 0059)
|
1. Santarli Construction Pte Ltd has been appointed as the builder for the Development of Bay East Gardens by the Ministry of National Development (MND) and Gardens by the Bay (GB). A silt curtain of approximately 10 m in length was installed at the Marina Reservoir, at the outlet of the public drain beneath the Benjamin Sheares Bridge (near the Event Plaza), in October 2025 (refer to the photo below). In view of the upcoming monsoon season, we would like to carry out enhancement works to the silt curtain to prevent any silty water discharge into the Marina Reservoir.

2. The schedule of works
|
Activities |
Start date / Time |
End date / Time |
|
Mobilization of work boat |
16 Dec 2025 |
16 Dec 2025 |
|
Silt curtain enhancement works (considering a few days due to wet weather), and boat will be demobilized from work location upon the completion of enhancement work. |
16 Dec 2025 |
26 Dec 2025 |
3. The location of works

4. Photos of Work Boats
Photo of RC 467 Catamaran Flotsam Retiever

Photo of RC 908 Workboat

Photo of RC 910 Workboat

- After the completion of daily work, the workboat will be anchored at the bridge abutment wall.