Date and Time |
Refer to schedule below |
|
Location |
Kallang Basin, Marina Reservoir
|
|
Craft |
SR3876H, SZH1894B (Work boat and safety boat), RZ073 (towing standby boat), SAF General Support Boats, Kairos Security boats
|
|
Contact |
Lim Wei Zhong NDP 2026 FW Committee
Adam Tan (Explomo Corporation Pte Ltd)
Kelvin Ho (Explomo Corporation Pte Ltd)
Kwek Teck Kee (Explomo Corporation Pte Ltd)
|
Table 2: Closure of Kallang Basin to all water traffic
|
Date |
Event |
Closure time |
|
27 Jun |
CR1 |
1400 hrs to 2200 hrs |
|
4 Jul |
CR2 |
|
|
11 Jul |
NE1 |
|
|
18 Jul |
NE2 |
|
|
25 Jul |
Preview 1 |
|
|
1 Aug |
Preview 2 |
|
|
9 Aug |
NDP 2026 |
Table 3: Details of Works at Kallang Basin (Republic Ave)
|
Date |
Time |
Activities |
Safety Remarks |
|
2 – 9 Jun 2026 |
0900 hrs- 1800 hrs |
Craning Ops at Kallang Basin (Republic Ave) Craning of office/store container and generator set @ Republic Ave Craning of store, equipment, wooden crates @ Republic Ave Configuration of cubis and pontoons at Kallang Basin (Republic Ave) |
All vessels are to keep clear of setup areas. (Refer to Map 1). |
|
9 Jun 2026 |
1000 hrs – 1800 hrs |
Reserve Date for Craning and Towing at Kallang Basin (Republic Ave) |
All vessels are to keep clear of setup areas. (Refer to Map 1). |
|
9 – 12 Jun 2026
(*Reserve date 12 Jun 2026) |
0900 hrs- 1800 hrs |
Towing of pontoons/ Cubi system from Kallang Basin (Republic Ave) to Kallang Basin for positioning and anchoring. Safety lines using line of floats and red buoys with flashing lights and no-entry signs will be installed. *Reserve date for towing ops |
All vessels are to keep a wide berth to the towing operations and keep clear of set up areas.
|
|
21 Jul, 28 Jul, (*Reserve date 24 Jun; 1, 8, 15, 24, 31 Jul; 6 Aug 2026) |
0900 hrs- 1800 hrs |
Transferring / towing of Mid cum high level fireworks from Kallang Sea Sports Training Center (KSTC) to Kallang Basin for installation process.
*Reserve date for transferring/ towing ops |
All vessels are to keep a wide berth to the towing operations and keep clear of set-up areas. |
|
23 - 27 Jun, |
1000 hrs– 2000 hrs |
Low/ Mid cum high level fireworks installation work in progress at Kallang Basin site.
Fireworks on site. |
All vessels are to keep a wide berth to the towing operations and keep clear of setup areas.
All vessels are to follow the navigational route in Map 2, 3 & 4. |
|
10 – 12 Aug
(*Reserve date 13 Aug 2026) |
0900 hrs-1800 hrs |
Removal of safety lines, red buoys and no-entry signs at Marina Bay. De-installation of pontoons. Towing of pontoons/ Cubi system from Marina Bay back to Kallang Basin (Republic Ave) for dismantling. *Reserve date for towing ops |
All vessels are to keep a wide berth to the towing operations and keep clear of tear-down areas. |
|
13 - 18 Aug 2026 (*Reserve date 18 Aug 2026) |
0900 hrs- 1800 hrs |
Dismantling works at Republic Ave. Recovery craning ops at Kallang Basin (Republic Ave). *Reserve date for craning ops |
All vessels are to keep clear of the tear-down areas. |
|
19 – 21 Aug 2026 (*Reserve 21 Aug 2026) |
0900 hrs- 1800 hrs |
Towing of dismantled cubis from Republic Ave to WWS
*Reserve date for towing ops |
All vessels are to keep clear of the tear-down areas. |